Cost of Construction in Singapore

A good rule of thumb that can be used in the Singapore context

  • Office Space  – 75-100 PSF
  • General Lab  100-150 PSF
  • Wet Lab  150-200 psf
  • Chemical lab 150-200 psf
  • GMP lab 250-350 psf
  • Cleanroom 500-600 psf

 

This would include basic fit out and not equipment. every building is different, with different levels of fit out and services; therefore it still makes sense to perform feasibility studies with respect to a site or multiple sites.

 

For example, some buildings might have floor, ceiling and ACMV fitted, others might be a blanks canvas even needed.